During the preconstruction estimate lock at the cafeteria dishwashing alcove, the ceiling tile area for acoustic ceiling tile is 4235 SF, with 8% attic stock and waste. A carton covers 64 SF. How many cartons should be ordered?
Correct Answer
D) 72 cartons
Carton quantity equals adjusted floor or ceiling area divided by carton coverage, rounded up.
Why This Is the Correct Answer
Carton quantity equals adjusted floor or ceiling area divided by carton coverage, rounded up.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the area summary schedule, what occupancy is listed for Zone D?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The Doral project has this exposure: overhead work is occurring above the crew. Which PPE action should be documented?
Next Question
While preparing the subcontractor quantity check for the retail demising-wall phase, the CMU wall area for block filler is 5275 SF and requires 3 coats. At 110 SF per gallon, how many gallons are required?