During the buyout verification pass at the senior-center activity hall, the shower wall area for cement backer board is 5160 SF. With 7% waste and 15 SF per sheet or panel, how many sheets are required?
Correct Answer
C) 369 sheets
Sheet count equals area with waste divided by coverage per sheet or panel, rounded up.
Why This Is the Correct Answer
Sheet count equals area with waste divided by coverage per sheet or panel, rounded up.
Why the Other Options Are Wrong
Option A: 344 sheets
344 sheets is below the supported result for cement backer board; it likely omits allowance, conversion, coverage, or final round-up.
Option B: 184 sheets
184 sheets is below the supported result for cement backer board; it likely omits allowance, conversion, coverage, or final round-up.
Option D: 373 sheets
373 sheets is above the supported result for cement backer board; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Cement cart for Carpenter Checks: sheet first, count second, whole the controlling choice last.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Tile substrate; board coverage; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass