Project MgmtConstructionmedium63% of exam part

During the next-week procurement cycle at the warehouse fire-pump room, the subgrade stabilization area for geotextile fabric covers 31300 SF, with 5% added for laps and cuts. Each roll covers 1350 SF. How many rolls are needed?

Correct Answer

C) 25 rolls

Roll count equals adjusted area divided by roll coverage, rounded up.

Answer Options
A
23 rolls
B
26 rolls
C
25 rolls
D
24 rolls

Why This Is the Correct Answer

Roll count equals adjusted area divided by roll coverage, rounded up.

Why the Other Options Are Wrong

Option A: 23 rolls

23 rolls is below the supported result for geotextile fabric; it likely omits allowance, conversion, coverage, or final round-up.

Option B: 26 rolls

26 rolls is above the supported result for geotextile fabric; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Option D: 24 rolls

24 rolls is below the supported result for geotextile fabric; it likely omits allowance, conversion, coverage, or final round-up.

Memory Technique

Measure to roll, adjust for count, then let Estimator Checks set the finish line.

Reference Hint

Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Earthwork; geotextile roll coverage; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.