During the material-order review at the town-hall records counter, the #7 pier cage bars takeoff has 126 bars at 10 ft each. Using 2.044 lb per ft for vertical cage bars, what reinforcing weight is estimated?
Correct Answer
A) 2,575 lb
Reinforcing weight equals bar count times length times pounds per foot.
Why This Is the Correct Answer
Reinforcing weight equals bar count times length times pounds per foot.
Why the Other Options Are Wrong
Option B: 1,260 lb
1,260 lb is below the supported result for #7 pier cage bars; it likely omits allowance, conversion, coverage, or final round-up.
Option C: 258 lb
258 lb is below the supported result for #7 pier cage bars; it likely omits allowance, conversion, coverage, or final round-up.
Option D: 2,884 lb
2,884 lb is above the supported result for #7 pier cage bars; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
# Pier Cage cart for Concrete Estimator: reinforcing first, weight second, whole units last.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Reinforcing steel; pier cage weight; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?