During the look-ahead planning meeting at the emergency-generator enclosure, a sanitary pipe run has a 72 ft run at 1.00% slope. What invert drop is required in inches?

Correct Answer

B) 8.6 in.

Convert run to inches and multiply by the slope percentage expressed as a decimal.

Answer Options
A
0.7 in.
B
8.6 in.
C
10.8 in.
D
9.3 in.

Why This Is the Correct Answer

Convert run to inches and multiply by the slope percentage expressed as a decimal.

Why the Other Options Are Wrong

Option A: 0.7 in.

0.7 in. is below the supported result for sanitary pipe run; it likely omits allowance, conversion, coverage, or final round-up.

Option C: 10.8 in.

10.8 in. is above the supported result for sanitary pipe run; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Option D: 9.3 in.

9.3 in. is above the supported result for sanitary pipe run; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Memory Technique

Measure to convert, adjust for inches, then let Field Engineer set the finish line.

Reference Hint

Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Plumbing coordination; pipe slope calculation; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.