During the field-takeoff reconciliation at the warehouse battery room, a scissor lift is needed for ceiling rough-in for 12 days at $185 per day, plus a $145 delivery charge. What rental cost should be budgeted?
Correct Answer
B) $2,365
Rental cost equals rental days times daily rate plus the delivery charge.
Why This Is the Correct Answer
Rental cost equals rental days times daily rate plus the delivery charge.
Why the Other Options Are Wrong
Option A: $2,220
$2,220 is below the supported result for scissor lift rental planning; it likely omits allowance, conversion, coverage, or final round-up.
Option C: $2,550
$2,550 is above the supported result for scissor lift rental planning; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option D: $3,960
$3,960 is above the supported result for scissor lift rental planning; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Superintendent Checks takeoff: count the condition before counting the package Tie the cue to Scissor Lift Rental Planning.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Equipment planning; aerial lift rental duration; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass