During the next-week procurement cycle at the surgery-suite support room, the gypsum board delivery includes 251 bundles of drywall bundles. Each delivery truck carries 24 bundles. How many truckloads are required?
Correct Answer
C) 11 truckloads
Truckloads equal total quantity divided by truck capacity, rounded up.
Why This Is the Correct Answer
Truckloads equal total quantity divided by truck capacity, rounded up.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
From panel schedule L3, what breaker is assigned to circuit L3-5?
Next Question
For the preconstruction estimate lock at the cafeteria dishwashing alcove, the open ceiling area for dryfall ceiling paint is 19150 SF and requires 1 coat. At 325 SF per gallon, how many gallons are required?