EstatePass
Project MgmtConstructionmedium63% of exam part

During the subcontractor quantity check at the data-room equipment alcove, a masonry crew must complete 10675 SF of CMU backup wall. If planned production is 780 SF per day, how many whole work days should be scheduled?

Correct Answer

A) 14 work days

Crew days equal quantity divided by daily production, rounded up to whole days.

Answer Options
A
14 work days
B
11 work days
C
16 work days
D
15 work days

Why This Is the Correct Answer

Crew days equal quantity divided by daily production, rounded up to whole days.

Why the Other Options Are Wrong

Option B: 11 work days

11 work days is below the supported result for cmu backup wall productivity; it likely omits allowance, conversion, coverage, or final round-up.

Option C: 16 work days

16 work days is above the supported result for cmu backup wall productivity; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Option D: 15 work days

15 work days is above the supported result for cmu backup wall productivity; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Memory Technique

Measure to crew, adjust for divided, then let Superintendent Schedules set the finish line.

Reference Hint

Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Masonry methods; crew production planning; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.