During the field-takeoff reconciliation at the storm-shelter entry vestibule, the mezzanine edge is 132 ft long and posts are placed at 8 ft on center, including one at the starting end. How many posts are needed?

Correct Answer

B) 17 posts

Count the spaces along the run, then include the starting item.

Answer Options
A
16 posts
B
17 posts
C
18 posts
D
19 posts

Why This Is the Correct Answer

Count the spaces along the run, then include the starting item.

Why the Other Options Are Wrong

Option A: 16 posts

16 posts is below the supported result for guardrail post layout; it likely omits allowance, conversion, coverage, or final round-up.

Option C: 18 posts

18 posts is above the supported result for guardrail post layout; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Option D: 19 posts

19 posts is above the supported result for guardrail post layout; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Memory Technique

Guardrail Post Layout cart for Foreman Checks: count first, spaces second, whole the controlling choice last.

Reference Hint

Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Temporary and permanent rail systems; post spacing; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.