During the field-takeoff reconciliation at the storm-shelter entry vestibule, the mezzanine edge is 132 ft long and posts are placed at 8 ft on center, including one at the starting end. How many posts are needed?
Correct Answer
B) 17 posts
Count the spaces along the run, then include the starting item.
Why This Is the Correct Answer
Count the spaces along the run, then include the starting item.
Why the Other Options Are Wrong
Option A: 16 posts
16 posts is below the supported result for guardrail post layout; it likely omits allowance, conversion, coverage, or final round-up.
Option C: 18 posts
18 posts is above the supported result for guardrail post layout; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option D: 19 posts
19 posts is above the supported result for guardrail post layout; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Guardrail Post Layout cart for Foreman Checks: count first, spaces second, whole the controlling choice last.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Temporary and permanent rail systems; post spacing; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?