During the material-order review at the bank drive-through canopy, the partition run is 108 ft long and studs are placed at 10 ft on center, including one at the starting end. How many studs are needed?

Correct Answer

A) 11 studs

Count the spaces along the run, then include the starting item.

Answer Options
A
11 studs
B
12 studs
C
13 studs
D
14 studs

Why This Is the Correct Answer

Count the spaces along the run, then include the starting item.

Why the Other Options Are Wrong

Option B: 12 studs

12 studs is above the supported result for metal stud layout; it likely adds an unsupported amount or compares the wrong financial base.

Option C: 13 studs

13 studs is above the supported result for metal stud layout; it likely adds an unsupported amount or compares the wrong financial base.

Option D: 14 studs

14 studs is above the supported result for metal stud layout; it likely adds an unsupported amount or compares the wrong financial base.

Memory Technique

Foreman Checks money test: bucket before math for metal stud layout.

Reference Hint

Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Cold-formed framing; stud spacing takeoff; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.