EstatePass
Project MgmtConstructionmedium63% of exam part

During the subcontractor quantity check at the airport rental-car counter, the dock apron slot requires 149 LF of trench drain frame plus 6% waste. Stock comes in 8 ft sections. How many sections are required?

Correct Answer

A) 20 sections

Linear stock count equals required length with waste divided by stock length, rounded up.

Answer Options
A
20 sections
B
19 sections
C
21 sections
D
22 sections

Why This Is the Correct Answer

Linear stock count equals required length with waste divided by stock length, rounded up.

Why the Other Options Are Wrong

Option B: 19 sections

19 sections is below the supported result for trench drain frame; it likely omits allowance, conversion, coverage, or final round-up.

Option C: 21 sections

21 sections is above the supported result for trench drain frame; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Option D: 22 sections

22 sections is above the supported result for trench drain frame; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Memory Technique

Trench Drain Frame cart for Field Engineer: linear first, stock second, whole units last.

Reference Hint

Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Specialty drainage; modular frame sections; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.