At the warehouse battery room, during the look-ahead planning meeting, the patio paving area for paver units is 5110 SF, with 12% attic stock and waste. A carton covers 18 SF. How many cartons should be ordered?
Correct Answer
A) 318 cartons
Carton quantity equals adjusted floor or ceiling area divided by carton coverage, rounded up.
Why This Is the Correct Answer
Carton quantity equals adjusted floor or ceiling area divided by carton coverage, rounded up.
Why the Other Options Are Wrong
Option B: 284 cartons
284 cartons is below the supported result for paver units; it likely omits allowance, conversion, coverage, or final round-up.
Option C: 332 cartons
332 cartons is above the supported result for paver units; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option D: 316 cartons
316 cartons is below the supported result for paver units; it likely omits allowance, conversion, coverage, or final round-up.
Memory Technique
Finishes Estimator takeoff: count the condition before counting the package Tie the cue to Paver Units Finishes Estimator.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Unit paving; carton coverage and waste; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?