At the visitor-center exhibit wall, during the field-takeoff reconciliation, the exposed beam run requires 368 LF of grade-beam forms at 2.0 ft high on 2 sides. What contact area is required?

Correct Answer

A) 1,472 SF

Form contact area equals length times height times the number of formed sides.

Answer Options
A
1,472 SF
B
736 SF
C
1,840 SF
D
1,473 SF

Why This Is the Correct Answer

Form contact area equals length times height times the number of formed sides.

Why the Other Options Are Wrong

Option B: 736 SF

736 SF is below the supported result for grade-beam forms; it likely omits allowance, conversion, coverage, or final round-up.

Option C: 1,840 SF

1,840 SF is above the supported result for grade-beam forms; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Option D: 1,473 SF

1,473 SF is above the supported result for grade-beam forms; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Memory Technique

Concrete Foreman takeoff: count the condition before counting the package.

Reference Hint

Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Concrete formwork; beam side forms; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.