At the courthouse records vault, during the preconstruction estimate lock, the #4 slab dowels takeoff has 132 bars at 16 ft each. Using 0.668 lb per ft for dowel stock, what reinforcing weight is estimated?
Correct Answer
C) 1,411 lb
Reinforcing weight equals bar count times length times pounds per foot.
Why This Is the Correct Answer
Reinforcing weight equals bar count times length times pounds per foot.
Why the Other Options Are Wrong
Option A: 2,112 lb
2,112 lb is above the supported result for #4 slab dowels; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option B: 88 lb
88 lb is below the supported result for #4 slab dowels; it likely omits allowance, conversion, coverage, or final round-up.
Option D: 1,580 lb
1,580 lb is above the supported result for #4 slab dowels; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Measure to reinforcing, adjust for weight, then let Concrete Estimator set the finish line.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Reinforcing steel; bar weight estimating; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass