Project MgmtConstructionmedium63% of exam part

At the clubhouse cart-storage bay, during the field-takeoff reconciliation, the membrane area for the low-slope recover totals 8200 SF. With 15% waste, how many roofing squares are needed?

Correct Answer

A) 94.3 squares

Roofing squares equal roof square feet with waste divided by 100.

Answer Options
A
94.3 squares
B
82.0 squares
C
1,047.8 squares
D
102.3 squares

Why This Is the Correct Answer

Roofing squares equal roof square feet with waste divided by 100.

Why the Other Options Are Wrong

Option B: 82.0 squares

82.0 squares is below the supported result for low-slope recover; it likely omits allowance, conversion, coverage, or final round-up.

Option C: 1,047.8 squares

1,047.8 squares is above the supported result for low-slope recover; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Option D: 102.3 squares

102.3 squares is above the supported result for low-slope recover; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Memory Technique

Roofing Estimator takeoff: count the condition before counting the package.

Reference Hint

Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Roof membrane systems; squares; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.