At the sports-field concession stand, during the preconstruction estimate lock, a concrete buggy is needed for interior slab placement for 5 days at $145 per day, plus a $340 delivery charge. What rental cost should be budgeted?
Correct Answer
C) $1,065
Rental cost equals rental days times daily rate plus the delivery charge.
Why This Is the Correct Answer
Rental cost equals rental days times daily rate plus the delivery charge.
Why the Other Options Are Wrong
Option A: $725
$725 is below the supported result for concrete buggy rental planning; it likely omits allowance, conversion, coverage, or final round-up.
Option B: $1,210
$1,210 is above the supported result for concrete buggy rental planning; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option D: $2,425
$2,425 is above the supported result for concrete buggy rental planning; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Concrete Buggy Rental cart for Superintendent Checks: cost first, days second, whole units last.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Concrete tools; buggy rental planning; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
