At the library reading-room addition, during the field-takeoff reconciliation, a portable light tower is needed for night concrete pour for 5 days at $96 per day, plus a $115 delivery charge. What rental cost should be budgeted?

Correct Answer

A) $595

Rental cost equals rental days times daily rate plus the delivery charge.

Answer Options
A
$595
B
$480
C
$691
D
$1,055

Why This Is the Correct Answer

Rental cost equals rental days times daily rate plus the delivery charge.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.