At the daycare classroom wing, during the next-week procurement cycle, the fence-panel order includes 264 panels at $42 each before a 18% contractor markup. What extended price should be carried?

Correct Answer

B) $13,084

Extended price equals quantity times unit price, then multiplied by the markup factor.

Answer Options
A
$11,088
B
$13,084
C
$13,638
D
$11,106

Why This Is the Correct Answer

Extended price equals quantity times unit price, then multiplied by the markup factor.

Why the Other Options Are Wrong

Option A: $11,088

$11,088 is below the supported result for temporary fence panels cost extension; it likely uses the wrong base, period, or account bucket.

Option C: $13,638

$13,638 is above the supported result for temporary fence panels cost extension; it likely adds an unsupported amount or compares the wrong financial base.

Option D: $11,106

$11,106 is below the supported result for temporary fence panels cost extension; it likely uses the wrong base, period, or account bucket.

Memory Technique

Estimator Prices money shelf: cost for markup, price for margin.

Reference Hint

Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Temporary facilities; rental material pricing; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.