At the restaurant grease-interceptor area, during the field-takeoff reconciliation, 166 sets are included in the door hardware prep. At 1.0 labor hours per set, how many labor hours are budgeted?
Correct Answer
A) 166.0 labor hours
Labor hours equal the number of units times the labor-hour factor per unit.
Why This Is the Correct Answer
Labor hours equal the number of units times the labor-hour factor per unit.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the area summary schedule, what occupancy is listed for Zone D?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A subcontractor asks for direction after noting that the project condition shows that base plate needs load-bearing grout. Which grout material best fits the work?
Next Question
During the material-order review at the maintenance-shop wash bay, the cricket infill zone measures 6669 SF before a 9% waste allowance. Each insulation board covers 32 SF. How many boards should be ordered?
