At the shipping-office break area, during the subcontractor quantity check, a drywall crew must complete 3675 SF of abuse-resistant board area. If planned production is 1390 SF per day, how many whole work days should be scheduled?
Correct Answer
D) 3 work days
Crew days equal quantity divided by daily production, rounded up to whole days.
Why This Is the Correct Answer
Crew days equal quantity divided by daily production, rounded up to whole days.
Why the Other Options Are Wrong
Option A: 2 work days
2 work days is below the supported result for abuse-resistant board area productivity; it likely omits allowance, conversion, coverage, or final round-up.
Option B: 5 work days
5 work days is above the supported result for abuse-resistant board area productivity; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option C: 4 work days
4 work days is above the supported result for abuse-resistant board area productivity; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Superintendent Schedules takeoff: count the condition before counting the package.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Interior partitions; drywall production planning; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass