At the hospital dietary expansion, during the material-order review, the mezzanine edge is 162 ft long and posts are placed at 4 ft on center, including one at the starting end. How many posts are needed?
Correct Answer
D) 41 posts
Count the spaces along the run, then include the starting item.
Why This Is the Correct Answer
Count the spaces along the run, then include the starting item.
Why the Other Options Are Wrong
Option A: 40 posts
40 posts is below the supported result for guardrail post layout; it likely omits allowance, conversion, coverage, or final round-up.
Option B: 42 posts
42 posts is above the supported result for guardrail post layout; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option C: 43 posts
43 posts is above the supported result for guardrail post layout; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Foreman Checks takeoff: count the condition before counting the package Tie the cue to Guardrail Post Layout Foreman.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Temporary and permanent rail systems; post spacing; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
For the buyout verification pass at the surgery-suite support room, the slab-on-grade footprint for vapor retarder covers 42550 SF, with 5% added for laps and cuts. Each roll covers 1000 SF. How many rolls are needed?
Next Question
A Florida superintendent must choose the proper site material because the controlling field constraint is that root growth must be redirected. Which option is best?