At the data-room equipment alcove, during the subcontractor quantity check, the stair return run requires 366 LF of handrail tube stock plus 6% waste. Stock comes in 20 ft lengths. How many lengths are required?
Correct Answer
D) 20 lengths
Linear stock count equals required length with waste divided by stock length, rounded up.
Why This Is the Correct Answer
Linear stock count equals required length with waste divided by stock length, rounded up.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the area summary schedule, what occupancy is listed for Zone D?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The work plan must account for this condition: substrate movement must be honored. Which tile joint detail is most suitable?
Next Question
At the stormwater-lift-station yard, during the field-takeoff reconciliation, the subgrade stabilization area for geotextile fabric covers 27300 SF, with 12% added for laps and cuts. Each roll covers 1350 SF. How many rolls are needed?