At the bank drive-through canopy, during the material-order review, a isolated mat footing is 51 ft by 10 ft by 4 in. Including 3% waste, how many cubic yards of concrete are needed?

Correct Answer

D) 6.5 CY

Convert slab thickness from inches to feet, divide by 27 cubic feet per cubic yard, then add waste.

Answer Options
A
6.3 CY
B
75.6 CY
C
7.3 CY
D
6.5 CY

Why This Is the Correct Answer

Convert slab thickness from inches to feet, divide by 27 cubic feet per cubic yard, then add waste.

Why the Other Options Are Wrong

Option A: 6.3 CY

6.3 CY is below the supported result for canopy column mat; it likely uses the wrong base, period, or account bucket.

Option B: 75.6 CY

75.6 CY is above the supported result for canopy column mat; it likely adds an unsupported amount or compares the wrong financial base.

Option C: 7.3 CY

7.3 CY is above the supported result for canopy column mat; it likely adds an unsupported amount or compares the wrong financial base.

Memory Technique

Canopy Column Mat drawer for Superintendent Validates: label convert before counting dollars.

Reference Hint

Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Concrete foundations; mat footing quantity; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.