Project MgmtConstructionmedium63% of exam part

For the crew-release check at the university bookstore shell, the roof edge zone for ice-and-water membrane covers 35550 SF, with 5% added for laps and cuts. Each roll covers 225 SF. How many rolls are needed?

Correct Answer

B) 166 rolls

Roll count equals adjusted area divided by roll coverage, rounded up.

Answer Options
A
158 rolls
B
166 rolls
C
175 rolls
D
165 rolls

Why This Is the Correct Answer

Roll count equals adjusted area divided by roll coverage, rounded up.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.