For the field-takeoff reconciliation at the seafood-market cooler room, the one-sided curb line requires 72 LF of curb forms at 3.5 ft high on 1 side. What contact area is required?
Correct Answer
D) 252 SF
Form contact area equals length times height times the number of formed sides.
Why This Is the Correct Answer
Form contact area equals length times height times the number of formed sides.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the area summary schedule, what occupancy is listed for Zone D?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The work plan must account for this condition: the controlling field constraint is that routine moisture is expected behind ceramic tile. Which tile substrate is most suitable?
Next Question
While preparing the subcontractor quantity check for the airport rental-car counter, the overhead pipe rack is 222 ft long and hangers are placed at 8 ft on center, including one at the starting end. How many hangers are needed?