For the preconstruction estimate lock at the college lab corridor, the #5 footing bars takeoff has 159 bars at 34 ft each. Using 1.043 lb per ft for continuous bar stock, what reinforcing weight is estimated?
Correct Answer
B) 5,638 lb
Reinforcing weight equals bar count times length times pounds per foot.
Why This Is the Correct Answer
Reinforcing weight equals bar count times length times pounds per foot.
Why the Other Options Are Wrong
Option A: 5,406 lb
5,406 lb is below the supported result for #5 footing bars; it likely omits allowance, conversion, coverage, or final round-up.
Option C: 166 lb
166 lb is below the supported result for #5 footing bars; it likely omits allowance, conversion, coverage, or final round-up.
Option D: 6,315 lb
6,315 lb is above the supported result for #5 footing bars; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Concrete Estimator takeoff: count the condition before counting the package.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Reinforcing steel; footing bar weight; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?