For the crew-release check at the retail vestibule replacement, a sidewalk cross-slope has a 60 ft run at 1.50% slope. What edge elevation difference is required in inches?
Correct Answer
B) 10.8 in.
Convert run to inches and multiply by the slope percentage expressed as a decimal.
Why This Is the Correct Answer
Convert run to inches and multiply by the slope percentage expressed as a decimal.
Why the Other Options Are Wrong
Option A: 0.9 in.
0.9 in. is below the supported result for sidewalk cross-slope; it likely omits allowance, conversion, coverage, or final round-up.
Option C: 13.5 in.
13.5 in. is above the supported result for sidewalk cross-slope; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option D: 11.5 in.
11.5 in. is above the supported result for sidewalk cross-slope; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Field Engineer takeoff: count the condition before counting the package Tie the cue to Sidewalk Cross-Slope Field Engineer.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Site concrete; cross-slope verification; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?