For the subcontractor quantity check at the maintenance-shop wash bay, a trench drain has a 108 ft run at 0.50% slope. What fall across the run is required in inches?
Correct Answer
C) 6.5 in.
Convert run to inches and multiply by the slope percentage expressed as a decimal.
Why This Is the Correct Answer
Convert run to inches and multiply by the slope percentage expressed as a decimal.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A Lake Mary guardrail layout is being checked before use. What nominal top-edge height should be used for the top rail?
Next Question
While preparing the crew-release check for the community-pool bathhouse, the patio paving area for paver units is 3045 SF, with 15% attic stock and waste. A carton covers 18 SF. How many cartons should be ordered?