For the next-week procurement cycle at the daycare classroom wing, 78 sleeves are included in the firestopping sleeve work. At 1.0 labor hours per sleeve, how many labor hours are budgeted?
Correct Answer
A) 78.0 labor hours
Labor hours equal the number of units times the labor-hour factor per unit.
Why This Is the Correct Answer
Labor hours equal the number of units times the labor-hour factor per unit.
Why the Other Options Are Wrong
Option B: 109.2 labor hours
109.2 labor hours is above the supported result for firestopping sleeve work; it likely pays the wrong premium tier or counts the same hours twice.
Option C: 66.3 labor hours
66.3 labor hours is below the supported result for firestopping sleeve work; it likely skips a premium-pay or employer-cost component.
Option D: 78.7 labor hours
78.7 labor hours is above the supported result for firestopping sleeve work; it likely pays the wrong premium tier or counts the same hours twice.
Memory Technique
Who controlled controlling, who paid units, where is the Manager Checks record?
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Firestopping methods; penetration labor; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?