Project MgmtConstructionmedium63% of exam part

The field condition is: the work should be released only if the team addresses that heat and wind may cause rapid slump loss and surface drying. Which placement control best matches the condition?

Correct Answer

D) Coordinate cooling shade timely discharge and curing

cooling shade timely discharge and curing best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.

Answer Options
A
Coordinate set-retarding admixture as approved
B
Coordinate evaporation reducer during finishing
C
Coordinate windbreaks and sunshades at the placement
D
Coordinate cooling shade timely discharge and curing

Why This Is the Correct Answer

cooling shade timely discharge and curing best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.

Why the Other Options Are Wrong

Option A: Coordinate set-retarding admixture as approved

Coordinate set-retarding admixture as approved may relate to another site control, but it does not remove or guard the hot weather concrete controls exposure being tested.

Option B: Coordinate evaporation reducer during finishing

Coordinate evaporation reducer during finishing may relate to another site control, but it does not remove or guard the hot weather concrete controls exposure being tested.

Option C: Coordinate windbreaks and sunshades at the placement

Coordinate windbreaks and sunshades at the placement may relate to another site control, but it does not remove or guard the hot weather concrete controls exposure being tested.

Memory Technique

Name the harm before the guard; set-retarding, admixture, approved cannot stand in for Manager Checking.

Reference Hint

Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Concrete placement methods; hot-weather handling and curing; verify the construction method, material selection, equipment choice, or work sequence that fits the field condition.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.