Project MgmtConstructionmedium63% of exam part

A Florida superintendent must choose the proper reinforcing method because the controlling field constraint is that bar continuity must meet detail. Which option is best?

Correct Answer

B) Select specified lap or mechanical splice

specified lap or mechanical splice best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.

Answer Options
A
Select random butt joint
B
Select specified lap or mechanical splice
C
Select welded splice without approval
D
Select wire tie treated as structural splice

Why This Is the Correct Answer

specified lap or mechanical splice best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.