The foreman is preparing the next work area, and the controlling field constraint is that truck cannot reach but hose route is practical. Which concrete placement equipment should be used?
Correct Answer
B) Select line pump with hose route
line pump with hose route best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.
Why This Is the Correct Answer
line pump with hose route best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
For the next-week procurement cycle at the clinic oxygen-storage pad, the #4 slab dowels takeoff has 141 bars at 24 ft each. Using 0.668 lb per ft for dowel stock, what reinforcing weight is estimated?
Next Question
At the industrial mezzanine landing, during the subcontractor quantity check, 90 locations are included in the casework blocking. At 0.5 labor hours per location, how many labor hours are budgeted?