During the pre-installation review, the field issue is that the project condition shows that alternate material must be reviewed before purchase. Which material substitution process is the best match?
Correct Answer
C) Use approved substitution before procurement
approved substitution before procurement best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.
Why This Is the Correct Answer
approved substitution before procurement best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the area summary schedule, what occupancy is listed for Zone D?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A Fort Pierce trench crew is placing excavated spoil beside the opening. What minimum distance from the edge should spoil and equipment be kept unless another protective method is used?
Next Question
For the next-week procurement cycle at the middle-school kitchen line, the subcontractor progress billing shows a $176,000 monthly earned value. If 10% is withheld, what retainage deduction should be shown?