In the look-ahead meeting, the constraint is that plaster movement must be controlled. Which stucco joint detail should the project team carry?

Correct Answer

D) control joints at required locations

control joints at required locations best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.

Answer Options
A
continuous plaster across movement break
B
lath fastened over joint opening
C
sealant replacing joint accessory
D
control joints at required locations

Why This Is the Correct Answer

control joints at required locations best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.