From the courtyard slab plan, what slab area should be used for quantity takeoff?
Correct Answer
B) 912 sf
The drawn slab dimensions are 38 ft by 24 ft, so the area is 912 sf.
Why This Is the Correct Answer
The drawn slab dimensions are 38 ft by 24 ft, so the area is 912 sf.
Why the Other Options Are Wrong
Option A: 848 sf
848 sf is below the supported result for dimensioned plan area takeoff; it likely omits allowance, conversion, coverage, or final round-up.
Option C: 1,024 sf
1,024 sf is above the supported result for dimensioned plan area takeoff; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option D: 1,176 sf
1,176 sf is above the supported result for dimensioned plan area takeoff; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Dimensioned Plan Area cart for Pricing Exterior: drawn first, slab second, whole sf last.
Reference Hint
Open-book path: turn to sheet A-121 in the plan packet, then use the COURTYARD SLAB PLAN note/table before checking P&P Commercial Construction plan-reading guidance.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?