A bidder submits a proposal while ignoring visible site conditions and available bidding documents. Which AIA A701 topic is implicated?
Correct Answer
C) Bidder representations about examining documents, site conditions, and bidding requirements
A701 includes bidder representations tied to review of documents and conditions.
Why This Is the Correct Answer
A701 includes bidder representations tied to review of documents and conditions.
Why the Other Options Are Wrong
Option A: Final completion and final payment after all punch work is done, and omit the issue from the current contract-administration log
Final completion and final payment after all punch work is done, and omit the issue from the current contract-administration log skips the written authority, scope, price, notice, or release control needed for bidder representations.
Option B: Subcontract payment provisions after the prime contract is complete, and use that shortcut to decide the bidder bidding conditions requirement, without confirming whether the duty belongs to owner or contractor
Subcontract payment provisions after the prime contract is complete, and use that shortcut to decide the bidder bidding conditions requirement, without confirming whether the duty belongs to owner or contractor skips the written authority, scope, price, notice, or release control needed for bidder representations.
Option D: Owner termination for convenience during the construction phase
Owner termination for convenience during the construction phase skips the written authority, scope, price, notice, or release control needed for bidder representations.
Memory Technique
Contract square for Reviews Obligations: scope, authority, price, paper.
Reference Hint
Open-book path: tab AIA A701-2018 to Article 4, Bidding Procedures; bidder representations; match the contract role, notice step, and timing in the stem before choosing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A Florida GC sees that one specification section implies a fire-rated assembly while the drawing note is less explicit. Under AIA A201, how should the project team treat the documents?
Next Question
The owner verbally asks for added signage during a walk-through. What should happen before work starts?