A Florida GC sees that one specification section implies a fire-rated assembly while the drawing note is less explicit. Under AIA A201, how should the project team treat the documents?
Correct Answer
A) Read the Contract Documents together as complementary requirements and seek interpretation if needed
A201 treats the Contract Documents as complementary and provides a contract path for interpretation.
Why This Is the Correct Answer
A201 treats the Contract Documents as complementary and provides a contract path for interpretation.
Why the Other Options Are Wrong
Option B: Let the drawing note erase all specification duties without written clarification
Let the drawing note erase all specification duties without written clarification skips the written authority, scope, price, notice, or release control needed for contract documents.
Option C: Ask the low trade bidder to select the cheapest interpretation for the assembly
Ask the low trade bidder to select the cheapest interpretation for the assembly skips the written authority, scope, price, notice, or release control needed for contract documents.
Option D: Treat the conflict as a final-payment issue rather than a construction issue, even though the contract record has not been updated
Treat the conflict as a final-payment issue rather than a construction issue, even though the contract record has not been updated skips the written authority, scope, price, notice, or release control needed for contract documents.
Memory Technique
When treats clashes with provides, let the contract speak before Interior Renovation.
Reference Hint
Open-book path: tab AIA A201-2017 to Article 1, Β§1.2 Correlation and Intent of the Contract Documents; match the contract role, notice step, and timing in the stem before choosing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?