The owner verbally asks for added signage during a walk-through. What should happen before work starts?

Correct Answer

B) Document owner request before work

Field changes need documentation and contract authorization.

Answer Options
A
Proceed from memory
B
Document owner request before work
C
Use weather report as authorization
D
Ask sign vendor to approve change

Why This Is the Correct Answer

Field changes need documentation and contract authorization.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.