Contract AdminContractsmedium40% of exam part

A written demand seeks extra payment and additional days because of an owner-caused impact. Under AIA A201, what is it generally called?

Correct Answer

A) A Claim under the contract's claims procedures

A201 defines Claims as demands or assertions seeking payment, time, or other relief.

Answer Options
A
A Claim under the contract's claims procedures
B
A bid addendum issued before bids are received, and use that shortcut to decide the claims requirement, while allowing an unapproved assumption to control the work
C
A certificate of substantial completion
D
A product data submittal for review

Why This Is the Correct Answer

A201 defines Claims as demands or assertions seeking payment, time, or other relief.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.