After reviewing the GC's application, who certifies the amount properly due to the contractor under AIA A201?

Correct Answer

C) The Architect certifies payment to the Owner based on the application review

A201 provides for Architect review and certification of amounts due.

Answer Options
A
The lowest bidder certifies because it established original pricing
B
The permit inspector certifies the contract payment amount, and treat the project meeting agenda as the contract instrument
C
The Architect certifies payment to the Owner based on the application review
D
The supplier with the largest invoice certifies final completion

Why This Is the Correct Answer

A201 provides for Architect review and certification of amounts due.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.