A glazing quote is $226,000 and the estimate carries 3.6% escalation. What amount should be used?

Correct Answer

D) $234,136

Add escalation to the quote.

Answer Options
A
$217,864
B
$230,520
C
$242,272
D
$234,136

Why This Is the Correct Answer

Add escalation to the quote.

Why the Other Options Are Wrong

Option A: $217,864

$217,864 is below the supported result for escalation; it likely omits allowance, conversion, coverage, or final round-up.

Option B: $230,520

$230,520 is below the supported result for escalation; it likely omits allowance, conversion, coverage, or final round-up.

Option C: $242,272

$242,272 is above the supported result for escalation; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Memory Technique

Reviews Glazing takeoff: count the condition before counting the package.

Reference Hint

Open-book path: tab Principles and Practices of Commercial Construction, 11th Edition, 2024 to Preconstruction estimating; escalation risk; verify quantity math, FL permit status, notice step, or field-control timing.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.