The contract states a required date for substantial completion. Which AIA A201 article organizes this obligation?
Correct Answer
C) Time provisions
A201 Article 8 addresses Contract Time, progress, and completion.
Why This Is the Correct Answer
A201 Article 8 addresses Contract Time, progress, and completion.
Why the Other Options Are Wrong
Option A: Insurance article only
Insurance article only skips the written authority, scope, price, notice, or release control needed for contract time.
Option B: Subcontract payment article
Subcontract payment article skips the written authority, scope, price, notice, or release control needed for contract time.
Option D: Bidder representation article
Bidder representation article skips the written authority, scope, price, notice, or release control needed for contract time.
Memory Technique
Confirms Completion shortcut is not a term until paper carries it.
Reference Hint
Open-book path: tab AIA A201-2017 to Article 8 Time; match the role, instrument, notice point, and timing before selecting.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?