The bidding documents require substitution requests before the bid. A trade offers an unapproved product at bid close. What should the GC do?
Correct Answer
C) Follow the specified substitution procedure
A701 bidding procedures and the project documents control substitution timing.
Why This Is the Correct Answer
A701 bidding procedures and the project documents control substitution timing.
Why the Other Options Are Wrong
Option A: Use the cheaper product and disclose it at final inspection
Use the cheaper product and disclose it at final inspection skips the written authority, scope, price, notice, or release control needed for substitution timing.
Option B: Treat a supplier quote as automatic design approval
Treat a supplier quote as automatic design approval skips the written authority, scope, price, notice, or release control needed for substitution timing.
Option D: List the product only in the pay application after award
List the product only in the pay application after award skips the written authority, scope, price, notice, or release control needed for substitution timing.
Memory Technique
Substitution Timing square for Receives Late: scope, authority, price, paper.
Reference Hint
Open-book path: tab AIA A701-2018 to Bidding Documents; substitutions and addenda procedures; verify the quantity, approval point, notice rule, or field record before answering.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?