Contract AdminPermitsmedium20% of exam part

The building department issues plan-review comments before permit approval. What is the correct administrative response?

Correct Answer

D) Route responses and revised documents through permit review

Plan review comments must be resolved through the permitting and design process before construction relies on the documents.

Answer Options
A
Start work from the rejected drawings because comments are only advisory after bid day
B
Have the subcontractor answer code comments on supplier letterhead without design review
C
Store the comments in the closeout binder and address them after occupancy
D
Route responses and revised documents through permit review

Why This Is the Correct Answer

Plan review comments must be resolved through the permitting and design process before construction relies on the documents.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.