A detail conflicts with the finish schedule before bids are due. What should the bidder do?

Correct Answer

B) Submit a prebid question through the required channel

Prebid conflicts should be handled through the bidding procedure and issued response.

Answer Options
A
Use the cheapest interpretation and omit the conflict from the bid file
B
Submit a prebid question through the required channel
C
Ask a supplier to rewrite the specification section for the architect
D
Save the conflict for warranty review after occupancy

Why This Is the Correct Answer

Prebid conflicts should be handled through the bidding procedure and issued response.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.