Contract AdminContractsmedium40% of exam part

Before ordering custom switchgear, the contractor asks for reasonable evidence that the owner can pay. Which AIA A201 topic applies?

Correct Answer

B) Evidence of the Owner's financial arrangements

A201 includes a process for reasonable evidence of the Owner's financial arrangements.

Answer Options
A
Architect approval of shop drawings for general conformance, while postponing the contract issue until closeout
B
Evidence of the Owner's financial arrangements
C
The contractor's cleanup duty at the end of each workday
D
The bidder's right to withdraw before bid receipt

Why This Is the Correct Answer

A201 includes a process for reasonable evidence of the Owner's financial arrangements.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.