A finish crew installs 46 door hardware sets per 8-hour day. The project has 184 sets. At $96 per labor hour for the crew, what labor amount should be carried?

Correct Answer

D) $3,072

Convert production into crew days and multiply by daily crew labor cost.

Answer Options
A
$2,208
B
$3,840
C
$4,416
D
$3,072

Why This Is the Correct Answer

Convert production into crew days and multiply by daily crew labor cost.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.