A worker takes a preventative cool-down rest in shade and reports heat symptoms. What should happen before the worker returns?
Correct Answer
C) Monitor and wait until symptoms abate.
A worker taking a cool-down rest must be monitored, asked about symptoms, and not ordered back until signs or symptoms have abated, with the minimum rest time still observed.
Why This Is the Correct Answer
A worker taking a cool-down rest must be monitored, asked about symptoms, and not ordered back until signs or symptoms have abated, with the minimum rest time still observed.
Why the Other Options Are Wrong
Option A: Send the worker home alone without first aid.
Send the worker home alone without first aid. may relate to another site control, but it does not remove or guard the outdoor heat illness prevention exposure being tested.
Option B: Order immediate return after one minute if production is behind.
Order immediate return after one minute if production is behind. may relate to another site control, but it does not remove or guard the outdoor heat illness prevention exposure being tested.
Option D: Replace the rest period with a lien-release form.
Replace the rest period with a lien-release form. may relate to another site control, but it does not remove or guard the outdoor heat illness prevention exposure being tested.
Memory Technique
Name the harm before the guard; send, worker, home cannot stand in for Responding Employee.
Reference Hint
Study anchor (closed-book): memorize Outdoor heat illness prevention from Cal/OSHA Title 8 Sections 3395 and 3396; CSLB Law and Business Study. / Title 8 Section 3395 cool-down rest; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?