A city hires your B contractor to repair a public library wall using city funds. What is the first CA public-works issue to check?
Correct Answer
A) Whether prevailing wage public-works rules apply.
Construction, alteration, demolition, installation, repair, and maintenance paid for with public funds can be public work, so prevailing wage duties must be evaluated.
Why This Is the Correct Answer
Construction, alteration, demolition, installation, repair, and maintenance paid for with public funds can be public work, so prevailing wage duties must be evaluated.
Why the Other Options Are Wrong
Option B: Whether private mechanics lien deadlines replace payroll records.
Whether private mechanics lien deadlines replace payroll records. misses the specific employer duty in public works coverage; it does not resolve the pay, reimbursement, status, timing, or record issue.
Option C: Whether the owner can waive all labor law duties in the bid form.
Whether the owner can waive all labor law duties in the bid form. misses the specific employer duty in public works coverage; it does not resolve the pay, reimbursement, status, timing, or record issue.
Option D: Whether the project becomes residential because the wall is indoors.
Whether the project becomes residential because the wall is indoors. misses the specific employer duty in public works coverage; it does not resolve the pay, reimbursement, status, timing, or record issue.
Memory Technique
If the job needs construction, the employer needs Reviewing Municipal proof.
Reference Hint
Study anchor (closed-book): memorize Public works coverage from California Labor Code public works and prevailing wage; DIR Public. / California Labor Code Sections 1720 and 1771; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?