Special-order doors are delivered, but the payment schedule is silent on stored-material billing. What should be checked?
Correct Answer
B) Payment schedule.
Material payment timing should be controlled by the written contract payment schedule and value delivered.
Why This Is the Correct Answer
Material payment timing should be controlled by the written contract payment schedule and value delivered.
Why the Other Options Are Wrong
Option A: Schedule of values.
Schedule of values. puts the item in the wrong financial bucket, timing, base, or comparison for material payment terms.
Option C: Signed credit change.
Signed credit change. puts the item in the wrong financial bucket, timing, base, or comparison for material payment terms.
Option D: Substantial completion.
Substantial completion. puts the item in the wrong financial bucket, timing, base, or comparison for material payment terms.
Memory Technique
An unlabeled Reviewing Invoice dollar tells the wrong story.
Reference Hint
Study anchor (closed-book): memorize Material payment terms from CSLB 2026 Law Book; CSLB Home Improvement Contracts / B&P Code Section 7159 home improvement contract requirements; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?